M5 Motorway Project

Example Slide

Location: Somerset

Contract Length: On Going Project

Scope of Work: Diesel Road Sawing 10,000 Linear Meters x 400mm Deep

Drillcut (UK) Limited were called upon to carry out the M5 motorway Road sawing project. The project consisted of 10,000m of motorway road surface to be cut through to 400mm deep asphalt and concrete to enable a new safety barrier to be installed on the live carriageway.

The project was to be completed on a very tight 2 week schedule to allow the barrier installation team to follow along behind to install a new safety barrier.

Drillcut (UK) Limited team mobilised 4nr. Diesel self propelled floor saw equipped with fully trained operatives to tandem floor saw. Drillcut (UK) Limited were self sufficient with there own power and water supply to carry out the required works. At the company’s HQ along with suppliers tried and tested the correct specification diamond tipped blades to maximise the progress and cost for the project.

The 4nr. operatives carried out the road sawing project in super efficient time completing all 10,000m of floor sawing in 7 normal working hours shifts.